Introduction of Power Transmission and Distribution Project
Issued Time :2015-02-04 15:17:13

1)Xicheng Substation Project in Yiyang

The project, located in west Bali lane of Yiyang County, is one of double-loop power supply modification projects in 2007 in Luoyang City of Henan Province.  

It is a 35KV substation and the outgoing distribution line is with capacity of 10KV, which solves the problem of double power supplies for 6 coal mines in Chengguan Village and Town. The foundation work of 2.8KM long 35KV double-loop line was finished on May 15, 2007. The basic line layout was finished on May 25, 2007. The equipment installation was finished on June 30, 2007.

O&M Power has successfully completed the HV equipment commissioning of the project.

2)Liuquan 110KV Substation Recontruction Project in Yiyang

The project, located in Liuquan Town of Yiyang County, is one of the grid modification projects for the villages in Luoyang City of Henan Province. The substation is expanded from 35KV to 110KV, which aims to meet the requirements of industrial and domestic power supply in Liuquan County. The project was started in August, 2008. The dismantling of the old units was completed on September 20, 2008. The replacement and installation was started in October, 2008, and the whole project was completed in September, 2009.

O&M Power has participated in the installation and commissioning of the project.

3)Wind-power 35KV Substation Project in North of Shaanxi

The wind power plant, located in Jinbian County of Shaanxi Province, consists of 12 wind generating units of capacity 1500KW for each. The total capacity of the power plant is 18MW. The 35KV substation is the supporting facilities of the project. The project was started in May, 2010 and completed for operation in April, 2011.
O&M Power was responsible for the commissioning of the project.

4)110KV Substation Project in Gaojia Town, Baoji

The project, located in Gaojia Town of Baoji City, Shaanxi Province, is one of grid modification projects for the villages in China. The substation adopts a new substation monitoring system, which realizes 24 hours unattended operation. The project was completed and put into service in May, 2009 and it is the first unattended substation project that O&M Power has ever participated in the construction. 

Unattended substation monitoring system consists of three parts: 1) front-terminal comprehensive monitoring equipment (Audio/video monitoring, environment variable monitoring, access monitoring, etc.), comprehensive monitoring host, comprehensive monitoring software. 2) Network transmission part (broadband, wireless network, ADSL or industrial user special network). 3) Management center software platform, unattended server, monitoring terminal, MIS network terminal, etc.

O&M Power has participated in the installation, commissioning and monitoring software development of the project.